Review of original design documents, including the equipment specifications and construction drawings (to be provided by State of CA), to assess Designed Capacity versus current utilization, targeting Capacity Planning for growth.
Review existing MEP single line.
Assess Current Distribution infrastructure for mechanical and electrical systems.
Review Design Intent / Basis of Design Criteria / Initial Capacity Intent
Evaluate current load on facility to determine remaining available capacities.
The Mechanical systems: assessment of the facility capacity and current utilization.
The Electrical systems: assessment of the facility capacity and current utilization.
The Mechanical systems: assessment of the facility mechanical distribution system
The Electrical systems: assessment of the facility mechanical distribution system
Capacity Availability Analysis.
Mission Critical Strategy development for maintaining uptime throughout the process.
Implementation of DCIM overlay for real-time utilization metrics.
UPS efficiency audit and comparative analysis between existing units and replacements.
Supplemental Mechanical Study of various methodologies for cooling/efficiency.
Coordinated Statement of Work and work on the logistics or progression of the ASTS
Script writing on oversight of the commissioning process through Level 5 IST.
|