Adobe
Client: Adobe, San Jose, California
Services: Commissioning
Date: September 2010


OVERVIEW

California Data Center Design Group (CDCDG) was retained by Adobe to commission three (3) sets of four (4) solid oxide fuel cells at their corporate headquarters in San Jose, California. Bloom Energy ES 5000 "Tucson" solid oxide fuel cells were selected for the project. The units use planar solid oxide fuel cell (SOFC) technology, first developed for NASA's Mars program.

SERVICES PROVIDED:

The project includes twelve (12) 100kW fuel cells located on the West Tower parking structure. This phase of the project provides a total of 4x100=400kW of 24/7 power for each tower, totaling 1200kW. New electrical equipment was installed on the output of the fuel cells to aggregate the power, step it up to Adobe's primary voltage service and distribute it to each of three (3) towers.

The commissioning process was designed to verify the individual components and the systems worked as designed.

Specifically, the commissioning verified that the fuels cells performed electrically within their specifications, the energy out vs. energy in. ratio is within published limits, the electrical distribution systems worked as designed and the Bloom Energy and IBS monitoring systems were accurate in their measurements and depiction of proper operations.


Our Clients
CDCDG was a pleasure to work with on the evaluation of our 131,000 square foot data center.
CDCDG was a tremendous help to us in figuring out our long term data center requirements.
CDCDG has been a real asset to us in helping us choose the location for our backup data center.
The commissioning process was effortless thanks to CDCDG.
From concept to commissioning CDCDG was an invaluable partner to us.
CDCDG's thorough evaluations of our statewide data center initiative has helped us to be a success.
It's been a pleasure working with you on another successful data center project.
Your support of our worldwide data center initiative has helped us to our success.
Your design oversight saved us thousands of dollars on our data center build.
We could not have done it without you.
 
News & Updates
  • April 2012: Ron Hughes, Founder of CDCDG steps down to take a position appointed by Governor... » More
  • March 2012: State of CA /CDCDG are nominated for GEIT Award for... » More
  • March 2012: KIO Networks / CDCDG are nominated for GEIT Award for Cutting Edge Data Center Design Category... » More
  • Feb 2012: CDCDG completes commissioning Porto Segura's primary data center... » More
» More